Ialomița, Romania
Gura Ialomiței Aukera BESS
Capacity
250 MW / 500 MWh
COD target
Phase 1 complete mid-2026; Phase 2 COD early 2027
Pricing
On enquiry
Chemistry
Not published
Interconnection
Transelectrica (voltage not published) · 50 Hz
One form — we email the desk and confirm to you.
250 MW / 500 MWh BESS at Gura Ialomiței — on completion, Romania’s largest battery and among the largest in CEE. Two-phase project finance (Kommunalkredit + IFC). CEENERGYNEWS / Aukera public print — not EnergyInfra-owned.
Location. Gura Ialomiței, Ialomița County, Romania.
Grid. Standalone BESS, Transelectrica / Romanian grid. Site in Gura Ialomiței.
Connection. Aukera (AtlasInvest / Reggeborgh / SFPIM) flagship. Phase 1: 150 MW / 300 MWh — construction completed June 2026 (€60m Kommunalkredit Austria, Nov 2025). Phase 2: 100 MW / 200 MWh — IFC €48.5m (€40m CapEx + €8.5m VAT), announced July 2026 (CEENERGYNEWS). Total debt >€100m. Asking price not published.
Offtake. Not disclosed in the public source.
Public source. CEENERGYNEWS, 26 July 2026; Aukera / EnergyNomics IFC close. Compiled from a public announcement or listing — not an EnergyInfra-owned asset and not a CIM. https://ceenergynews.com/finance/aukera-romania-storage-bess/